Describe the bug
setting color to a specific day is not working for a general diagram without start date
To Reproduce
@startgantt
[C] lasts 10 days
[C] starts at D+10
D+5 to D+7 are colored in blue
D+10 is colored in gold
footer \n(current version: %version())
@endgantt
Expected behavior
mentioned days are colored
Screenshots
actual result for latest version
Additional context
the coloring works fine if i add a project start date (i.e. "project starts the 2021/01/10"), however this changes a project timeline as well. I would like to mark specific days without connecting project timeline to a calendar.